Milestones

  • Active Travel Funding approved

    April 2021

     

    -

     

    March 2022

    Welsh Government agree funding for design and feasibility of an active travel route connecting Barry to Dinas Powys.
  • Route option consultation

    July 2022

     

    -

     

    August 2022

    Public asked which route option they would prefer the Council to design.
  • Concept design

    September 2022

     

    -

     

    March 2024

    Work on preferred option for design of active travel route recommended by public consultation.
  • Consultation on route design

    May 2024

     

    -

     

    June 2024

    Collect feeback on the Councils proposed active travel route.
  • Complete detailed design

    June 2024

     

    -

     

    December 2024

    Complete all necessary tasks on the detailed design of the route.
  • Apply for construction funding

    January 2025

     

    -

     

    March 2025

    Bid for construction funding from Welsh Government.